Court St/Western Ave Shared Use Path

Greenway in Massachusetts

Runs through Westfield · Hampden County

Conditions now

Loading the weather near Westfield…

Forecast by the National Weather Service for Westfield · Forecast at weather.gov

Live from the National Weather Service, NOAA river gauges and the National Interagency Fire Center as this page opened. Advisories, not closure orders: follow the links for the agency's details.

Length
2.7 mi 4.4 km1
Surface
Paved1
Last checked
Oct 31, 2026

Trailheads

  1. Parking at Western Avenue mile 0 directions to trailhead 1
  2. Parking at Western Avenue mile 0 directions to trailhead 2
  3. Parking at Ely Road mile 0.1 directions to trailhead 3
  4. Parking at Ely Road mile 0.1 directions to trailhead 4
  5. Parking at Stockton Road mile 0.2 directions to trailhead 5
  6. Parking at Parenzo Road West mile 0.3 directions to trailhead 6
  7. Parking at Parenzo Road East mile 0.3 directions to trailhead 7
  8. Parking at Western Avenue mile 0.4 directions to trailhead 8
  9. Parking at Western Avenue mile 0.5 directions to trailhead 9
  10. Parking at Western Avenue mile 0.6 directions to trailhead 10
  11. Parking at Gillett Road mile 0.7 directions to trailhead 11
  12. Parking at Western Avenue mile 1 directions to trailhead 12
  13. Parking at Western Avenue mile 1.8 directions to trailhead 13
  14. Parking at Court Street mile 2.3 directions to trailhead 14
  15. Parking at Cortez Street mile 2.5 directions to trailhead 15
  16. Parking at King Street mile 2.6 directions to trailhead 16
  17. Parking at Day Avenue mile 2.6 directions to trailhead 17
  18. Parking at Court Street mile 2.6 directions to trailhead 18
  19. Parking at Court Street mile 2.6 directions to trailhead 19
  20. Parking at Central Street mile 2.7 directions to trailhead 20
  21. Parking at Pleasant Street mile 2.7 directions to trailhead 21
  22. Parking at Court Street mile 2.7 directions to trailhead 22
  23. Parking at Central Street mile 2.8 directions to trailhead 23
  24. Parking at Central Street mile 2.8 directions to trailhead 24
  25. Parking at Central Street mile 2.8 directions to trailhead 25
  26. Parking at Court Street mile 2.8 directions to trailhead 26
  27. Parking at Holland Avenue mile 2.8 directions to trailhead 27
  28. Parking at Holland Avenue mile 2.8 directions to trailhead 28
  29. Parking at Pleasant Street mile 2.8 directions to trailhead 29
Westfield, along the trail (opens in a new tab)
Westfield, along the trail · Photo: Jeff Jason II (jeffjason.com) AKA UmassThrower (talk) · CC BY-SA 3.0 · Wikimedia Commons

No photo of the trail itself yet. Ridden it? Add yours.

About this trail

The Court Street/Western Avenue Shared Use Path is a paved shared-use path of about 2.7 miles along Western Avenue and Court Street in Westfield, Massachusetts, part of the Route 20 corridor. The City of Westfield built it with state and federal aid as part of a two-phase reconstruction of the streets meant to improve safety and access for pedestrians and bicyclists. It runs mainly on the north side of the road, past Westfield State University and Stanley Park and on toward downtown.

The Central Phase rebuilt about 1.4 miles of Western Avenue from Llewellyn Avenue to Lloyds Hill Road and added a 10-foot path on the north side of the avenue; it was under construction in 2019 with completion scheduled for fall 2020. The East Phase, MassDOT project 607773, was presented at a public hearing on September 12, 2019. It extended a 10-foot path along the north side of Western Avenue and Court Street from Lloyds Hill Road to High Street and Mill Street and on the south side of Court Street to Holcomb Street, with an 8- to 9-foot path on Lloyds Hill Road and walkways through Holcomb Park. In September 2022 MassDOT expected that work to be finished in September 2023.

The path is set apart from 10-foot travel lanes with 5-foot shoulders that serve as bicycle accommodation. The project added a signal with a pedestrian phase at the Westfield State University driveway and mid-block crossings with raised medians. East of Lloyds Hill Road the path passes mostly residential land and Pine Hill Cemetery, near the junction of Western Avenue and Court Street.

Sources checked Oct 13, 2026 · CC BY 4.0

History and riding conditions

From federal and state maps, matched to the trail's mapped line.

Shade

21% tree cover along the route: partly shaded. Tree canopy at 100 points along the trail, 2025 data.

When to ride

Best months: April to October. Months with normal highs of 55 to 85 °F, under an inch of snow and under 5 inches of precipitation.

Monthly normals, 1991–2020
Westfield Barnes Municipal Airport, 6.3 km from the trail's middle, 10 m higher
NormalJanFebMarAprMayJunJulAugSepOctNovDec
High °F353847607280858375635140
Low °F161726354655615951393022
Precipitation, in2.82.63.44.13.74.44.23.74.64.73.53.6
On the National Register
Old maps

USGS topographic maps of the trail's middle go back to the 1887 Granville sheet (1:62,500); the 1958 Southwick sheet (1:24,000) shows the area at mid-century. Browse all 25 maps in topoView.

Sources: National Register of Historic Places locations (National Park Service) (Public domain); Historical Topographic Map Collection (U.S. Geological Survey) (Public domain); NLCD Tree Canopy Cover (USDA Forest Service) (Public domain); U.S. Climate Normals 1991-2020 (NOAA National Centers for Environmental Information) (Public domain). Matched Nov 3, 2026. Map layers are approximate: a fact here is a lead to check, not a survey.

Nearby trails

Take it with you

Download GPX GeoJSON

Open data, ODbL. Attribute BikeTheRail and OpenStreetMap contributors.

Something wrong?

Closed section, wrong surface, missing piece? Tell us and a person will check it. Report a problem.

Sources

  1. OpenStreetMap ways for this trail, OpenStreetMap contributors · Map data · ODbL · checked Oct 31, 2026
  2. Certificate on the Notice of Project Change, Access Improvements to Western Avenue – East Phase, EEA #15835 — Massachusetts Executive Office of Energy and Environmental Affairs (January 22, 2021) · government source · checked Oct 13, 2026
    Supports: City of Westfield as proponent, two-phase purpose, Central Phase of 1.4 miles from Llewellyn Avenue to Lloyd Hill Road with a 10-foot path on the north side, East Phase path limits to High Street/Mill Street and Holcomb Street, Lloyds Hill Road path, Holcomb Park paths, 10-foot lanes and 5-foot shoulders, WSU signal, mid-block crossings with raised medians, Stanley Park and WSU, residential land and Pine Hill Cemetery
  3. WESTFIELD - Improvements & Related Work on Route 20, Court Street & Western Avenue (Phase II) — Mass.gov (MassDOT Highway Division) · government source · checked Oct 13, 2026
    Supports: Route 20 corridor, September 12, 2019 hearing, project file 607773, multi-use path along Western Avenue, 5-foot shoulders for bicycles
  4. Phase II of Western Avenue project reviewed — The Westfield News (September 16, 2019) · press · checked Oct 13, 2026
    Supports: Phase I under construction with completion scheduled for fall 2020, Phase II path continuing onto Court Street, state and federal funding shares
  5. Getting Answers: Western Ave. road concerns in Westfield — Western Mass News (September 27, 2022) · press · checked Oct 13, 2026
    Supports: MassDOT expecting completion in September 2023, Western Avenue, West Silver Street and Court Street work in 2023

Every fact above cites a numbered source and the date it was last checked; the list is rebuilt weekly. Know a better source? Add a reference.